Author: Rausch Infrastructure

November 2025 Update

December 5, 2025 Rausch Infrastructure

The connecting structure was completed in November. The slide gate barrel section was cast with antimicrobial admixtures and waterproofing membrane,…

Continue Reading →

October 2025 Update

November 7, 2025 Rausch Infrastructure

October’s progress consisted of installation of the slide gate which included diversion of the 66″ diameter sewer pipe, drilling and…

Continue Reading →

September 2025 Update

October 9, 2025 Rausch Infrastructure

September began with the removal of the H-Pile and lagging earth retention system and partially completing the backfill of the…

Continue Reading →

August 2025 Progress Update

September 17, 2025 Rausch Infrastructure

August progress consisted of forming of the walls of the connecting structure, installation of rebar for the walls, and the…

Continue Reading →

July 2025 Update

August 12, 2025 Rausch Infrastructure

Rausch remobilized to the site in June to prepare for the excavation for the restart of the connecting structure work.…

Continue Reading →

October Progress Update

November 11, 2024 Rausch Infrastructure

October progress consisted of landscape restoration of the south portion of the project around the existing access manhole and replacement…

Continue Reading →

September Progress Update

October 9, 2024 Rausch Infrastructure

September consisted of restoring to existing conditions for the staging area near the access manhole. Rausch removed the temporary stone…

Continue Reading →

August Progress Update

September 10, 2024 Rausch Infrastructure

The barrel shaft modification was completed to allow for the grating to be installed. Once the concrete work was completed…

Continue Reading →

July Progress Update

August 13, 2024 Rausch Infrastructure

July progress consisted of completing the barrel wall thickening and preparing for the top slab modification of the access manhole…

Continue Reading →

June Progress Update

July 11, 2024 Rausch Infrastructure

Rausch Infrastructure remobilized back to the project site to complete the work of the barrel shaft wall thickening and backfilling…

Continue Reading →

Post navigation

Page 1 of 3
1 2 3 Next →

Recent Posts

  • November 2025 Update
  • October 2025 Update
  • September 2025 Update
  • August 2025 Progress Update
  • July 2025 Update

Recent Comments

No comments to show.
  • Starting: Spring 2023
  • Estimated Completion: Fall 2025
  • Contract: Rausch Infrastructure, LLC
  • Contact: Anthony Rausch 708-667-0165