The connecting structure was completed in November. The slide gate barrel section was cast with antimicrobial admixtures and waterproofing membrane,…
October’s progress consisted of installation of the slide gate which included diversion of the 66″ diameter sewer pipe, drilling and…
September began with the removal of the H-Pile and lagging earth retention system and partially completing the backfill of the…
August progress consisted of forming of the walls of the connecting structure, installation of rebar for the walls, and the…
Rausch remobilized to the site in June to prepare for the excavation for the restart of the connecting structure work.…
October progress consisted of landscape restoration of the south portion of the project around the existing access manhole and replacement…
September consisted of restoring to existing conditions for the staging area near the access manhole. Rausch removed the temporary stone…
The barrel shaft modification was completed to allow for the grating to be installed. Once the concrete work was completed…
July progress consisted of completing the barrel wall thickening and preparing for the top slab modification of the access manhole…
Rausch Infrastructure remobilized back to the project site to complete the work of the barrel shaft wall thickening and backfilling…