October’s progress consisted of installation of the slide gate which included diversion of the 66″ diameter sewer pipe, drilling and anchoring slide gate into place, grouting around the slide gate and pouring the blockout of the flow channel back into place.
Once the slide gate was installed the diversion was removed, the precast SIP forms were installed and the top slab was poured. October finished with the pouring of the riser section above the slide gate.
Project is on track to be completed in November.