July 2025 Update

Rausch remobilized to the site in June to prepare for the excavation for the restart of the connecting structure work. Much of the formwork, reinforcing steel, and mud slab was covered in sediment which was cleaned and a stone drain was placed around the perimeter of the formwork in order to dewater for the base slab pour.

In July the rebar installation was completed for the base slab and the base slab was poured and now the structure walls are in progress.