May did not have construction progress. Rausch Infrastructure demobilized from the site while change orders were being processed.
With the concrete for the barrel reconstruction fully cured, April’s progress was the installation of the CFRP liner system.
In March the barrel reconstruction was completed and the RCP elbow was encased in concrete. Sections of the trench for…
February’s progress consisted of installing the custom fabricated RCP elbow and the last length of 48″ RCP. The concrete cradle…
Happy New Year! During the month of January, the concrete demolition of the barrel for the connection to the existing…
During December, rebar and formwork was installed for the connecting structure base mat and walls. The 48″ reinforced concrete pipe…
During November, underneath the pipes were fully excavated and a mud slab was installed to begin the construction of the…
During October, the excavation was completed and reached grade with the lagging boards installed to the bottom of the excavation.…
During September, the waler installation was completed and excavation and lagging installation began. The excavation is approximately 80% complete.
During August, the H-Piles for the earth retention system were driven to grade and excavation, lagging installation, and waler installation…