Author: Rausch Infrastructure

May Progress Update

July 11, 2024 Rausch Infrastructure

May did not have construction progress. Rausch Infrastructure demobilized from the site while change orders were being processed.

Continue Reading →

April Progress Update

May 10, 2024 Rausch Infrastructure

With the concrete for the barrel reconstruction fully cured, April’s progress was the installation of the CFRP liner system.

Continue Reading →

March Progress Update

April 11, 2024 Rausch Infrastructure

In March the barrel reconstruction was completed and the RCP elbow was encased in concrete. Sections of the trench for…

Continue Reading →

February Progress Update

March 11, 2024 Rausch Infrastructure

February’s progress consisted of installing the custom fabricated RCP elbow and the last length of 48″ RCP. The concrete cradle…

Continue Reading →

January Progress Update

February 6, 2024 Rausch Infrastructure

Happy New Year! During the month of January, the concrete demolition of the barrel for the connection to the existing…

Continue Reading →

December Progress Update

January 10, 2024 Rausch Infrastructure

During December, rebar and formwork was installed for the connecting structure base mat and walls. The 48″ reinforced concrete pipe…

Continue Reading →

November Progress Update

December 6, 2023 Rausch Infrastructure

During November, underneath the pipes were fully excavated and a mud slab was installed to begin the construction of the…

Continue Reading →

October Progress Update

November 7, 2023 Rausch Infrastructure

During October, the excavation was completed and reached grade with the lagging boards installed to the bottom of the excavation.…

Continue Reading →

September Progress Update

October 10, 2023 Rausch Infrastructure

During September, the waler installation was completed and excavation and lagging installation began. The excavation is approximately 80% complete.

Continue Reading →

August Progress Update

September 13, 2023 Rausch Infrastructure

During August, the H-Piles for the earth retention system were driven to grade and excavation, lagging installation, and waler installation…

Continue Reading →

Post navigation

Page 2 of 3
← Previous 1 2 3 Next →

Recent Posts

  • November 2025 Update
  • October 2025 Update
  • September 2025 Update
  • August 2025 Progress Update
  • July 2025 Update

Recent Comments

No comments to show.
  • Starting: Spring 2023
  • Estimated Completion: Fall 2025
  • Contract: Rausch Infrastructure, LLC
  • Contact: Anthony Rausch 708-667-0165