Skip to content
Calumet18E Relief Connecting Structure and Sewer Work
Calumet18E Relief Connecting Structure and Sewer Work
MWRD Contract No. 21-262-3S
  • Home
  • About
  • News
  • Contact Us

Author: Rausch Infrastructure

June Progress Update

July 11, 2024 Rausch Infrastructure

Rausch Infrastructure remobilized back to the project site to complete the work of the barrel shaft wall thickening and backfilling…

Continue Reading →

May Progress Update

Rausch Infrastructure

May did not have construction progress. Rausch Infrastructure demobilized from the site while change orders were being processed.

Continue Reading →

April Progress Update

May 10, 2024 Rausch Infrastructure

With the concrete for the barrel reconstruction fully cured, April’s progress was the installation of the CFRP liner system.

Continue Reading →

March Progress Update

April 11, 2024 Rausch Infrastructure

In March the barrel reconstruction was completed and the RCP elbow was encased in concrete. Sections of the trench for…

Continue Reading →

February Progress Update

March 11, 2024 Rausch Infrastructure

February’s progress consisted of installing the custom fabricated RCP elbow and the last length of 48″ RCP. The concrete cradle…

Continue Reading →

January Progress Update

February 6, 2024 Rausch Infrastructure

Happy New Year! During the month of January, the concrete demolition of the barrel for the connection to the existing…

Continue Reading →

December Progress Update

January 10, 2024 Rausch Infrastructure

During December, rebar and formwork was installed for the connecting structure base mat and walls. The 48″ reinforced concrete pipe…

Continue Reading →

November Progress Update

December 6, 2023 Rausch Infrastructure

During November, underneath the pipes were fully excavated and a mud slab was installed to begin the construction of the…

Continue Reading →

October Progress Update

November 7, 2023 Rausch Infrastructure

During October, the excavation was completed and reached grade with the lagging boards installed to the bottom of the excavation.…

Continue Reading →

September Progress Update

October 10, 2023 Rausch Infrastructure

During September, the waler installation was completed and excavation and lagging installation began. The excavation is approximately 80% complete.

Continue Reading →

Post navigation

Page 2 of 3
← Previous 1 2 3 Next →

Recent Posts

  • April 2026 Update
  • November 2025 Update
  • October 2025 Update
  • September 2025 Update
  • August 2025 Progress Update

Recent Comments

No comments to show.
  • Starting: Spring 2023
  • Estimated Completion: Fall 2025
  • Contract: Rausch Infrastructure, LLC
  • Contact: Anthony Rausch 708-667-0165
Copyright © 2026 Calumet18E Relief Connecting Structure and Sewer Work