April/May Progress Update

Work on the project began at the end of April with the excavation for the temporary access road which will provide uninterrupted access to the MWRD and IDOT facilities on the MWRD Access Drive.

May progress consisted of tree clearing, installing the temporary access road, delivery of earth retention materials, and fencing off the project site.

Work is currently suspended until ComEd performs a relocation of a guy wire conflicting with the temporary access road clearances. Work will resume at the end of June once this relocation has been completed.