Happy New Year! During the month of January, the concrete demolition of the barrel for the connection to the existing manhole access shaft took place. The concrete in this area was approximately 3′ thick and posed a challenge for removing it due to the size, weight, and relatively tight quarters to remove the pieces. Once all the pieces were removed the area was prepared for the prefrabricated RCP elbow to be installed.