During December, rebar and formwork was installed for the connecting structure base mat and walls. The 48″ reinforced concrete pipe was also installed, along with concrete cradle and initial backfill. A temporary platform was installed on the manhole access shaft to allow for the upcoming CFRP work to be performed.