October progress consisted of landscape restoration of the south portion of the project around the existing access manhole and replacement…
September consisted of restoring to existing conditions for the staging area near the access manhole. Rausch removed the temporary stone…
The barrel shaft modification was completed to allow for the grating to be installed. Once the concrete work was completed…
July progress consisted of completing the barrel wall thickening and preparing for the top slab modification of the access manhole…
Rausch Infrastructure remobilized back to the project site to complete the work of the barrel shaft wall thickening and backfilling…
May did not have construction progress. Rausch Infrastructure demobilized from the site while change orders were being processed.
With the concrete for the barrel reconstruction fully cured, April’s progress was the installation of the CFRP liner system.
In March the barrel reconstruction was completed and the RCP elbow was encased in concrete. Sections of the trench for…
February’s progress consisted of installing the custom fabricated RCP elbow and the last length of 48″ RCP. The concrete cradle…
Happy New Year! During the month of January, the concrete demolition of the barrel for the connection to the existing…