Author: Rausch Infrastructure

October Progress Update

November 11, 2024 Rausch Infrastructure

October progress consisted of landscape restoration of the south portion of the project around the existing access manhole and replacement…

Continue Reading →

September Progress Update

October 9, 2024 Rausch Infrastructure

September consisted of restoring to existing conditions for the staging area near the access manhole. Rausch removed the temporary stone…

Continue Reading →

August Progress Update

September 10, 2024 Rausch Infrastructure

The barrel shaft modification was completed to allow for the grating to be installed. Once the concrete work was completed…

Continue Reading →

July Progress Update

August 13, 2024 Rausch Infrastructure

July progress consisted of completing the barrel wall thickening and preparing for the top slab modification of the access manhole…

Continue Reading →

June Progress Update

July 11, 2024 Rausch Infrastructure

Rausch Infrastructure remobilized back to the project site to complete the work of the barrel shaft wall thickening and backfilling…

Continue Reading →

May Progress Update

Rausch Infrastructure

May did not have construction progress. Rausch Infrastructure demobilized from the site while change orders were being processed.

Continue Reading →

April Progress Update

May 10, 2024 Rausch Infrastructure

With the concrete for the barrel reconstruction fully cured, April’s progress was the installation of the CFRP liner system.

Continue Reading →

March Progress Update

April 11, 2024 Rausch Infrastructure

In March the barrel reconstruction was completed and the RCP elbow was encased in concrete. Sections of the trench for…

Continue Reading →

February Progress Update

March 11, 2024 Rausch Infrastructure

February’s progress consisted of installing the custom fabricated RCP elbow and the last length of 48″ RCP. The concrete cradle…

Continue Reading →

January Progress Update

February 6, 2024 Rausch Infrastructure

Happy New Year! During the month of January, the concrete demolition of the barrel for the connection to the existing…

Continue Reading →

Post navigation

Page 1 of 2
1 2 Next →

Recent Posts

  • October Progress Update
  • September Progress Update
  • August Progress Update
  • July Progress Update
  • June Progress Update

Recent Comments

No comments to show.
  • Starting: Spring 2023
  • Estimated Completion: Fall 2023
  • Contract: Rausch Infrastructure, LLC
  • Contact: Anthony Rausch 708-667-0165