The ComEd guy wire relocation was performed at the end of June, this allowed for the IDOT/MWRD Access Drive to be closed and for traffic to be routed to the temporary driveway.
July progress consisted of installation of H-Pile beams for the earth retention system. Pile installation is expected to be complete the first week of August at which point excavation will begin.