July Progress Update

July progress consisted of completing the barrel wall thickening and preparing for the top slab modification of the access manhole shaft. The grating insert was prepared and placed into the formwork and the rebar is being erected to complete the pour.

Road backfill was completed and Tyro Construction completed the HMA road restoration.