December Progress Update

During December, rebar and formwork was installed for the connecting structure base mat and walls. The 48″ reinforced concrete pipe was also installed, along with concrete cradle and initial backfill. A temporary platform was installed on the manhole access shaft to allow for the upcoming CFRP work to be performed.