Skip to content
Calumet18E Relief Connecting Structure and Sewer Work
Calumet18E Relief Connecting Structure and Sewer Work
MWRD Contract No. 21-262-3S
  • Home
  • About
  • News
  • Contact Us

Author: Rausch Infrastructure

December Progress Update

January 10, 2024 Rausch Infrastructure

During December, rebar and formwork was installed for the connecting structure base mat and walls. The 48″ reinforced concrete pipe…

Continue Reading →

November Progress Update

December 6, 2023 Rausch Infrastructure

During November, underneath the pipes were fully excavated and a mud slab was installed to begin the construction of the…

Continue Reading →

October Progress Update

November 7, 2023 Rausch Infrastructure

During October, the excavation was completed and reached grade with the lagging boards installed to the bottom of the excavation.…

Continue Reading →

September Progress Update

October 10, 2023 Rausch Infrastructure

During September, the waler installation was completed and excavation and lagging installation began. The excavation is approximately 80% complete.

Continue Reading →

August Progress Update

September 13, 2023 Rausch Infrastructure

During August, the H-Piles for the earth retention system were driven to grade and excavation, lagging installation, and waler installation…

Continue Reading →

June/July Progress Update

August 15, 2023 Rausch Infrastructure

The ComEd guy wire relocation was performed at the end of June, this allowed for the IDOT/MWRD Access Drive to…

Continue Reading →

April/May Progress Update

June 9, 2023 Rausch Infrastructure

Work on the project began at the end of April with the excavation for the temporary access road which will…

Continue Reading →

Post navigation

Page 2 of 2
← Previous 1 2

Recent Posts

  • October Progress Update
  • September Progress Update
  • August Progress Update
  • July Progress Update
  • June Progress Update

Recent Comments

No comments to show.
  • Starting: Spring 2023
  • Estimated Completion: Fall 2023
  • Contract: Rausch Infrastructure, LLC
  • Contact: Anthony Rausch 708-667-0165
Copyright © 2025 Calumet18E Relief Connecting Structure and Sewer Work